Corio Generation and bp Alternative Energy Investment Ltd invest in South Korea Australia missing climate targets Advocating for US based offshore wind Broken Record, Temperatures hit new highs, yet world fails to cut emissions (again) Toshiba and GE to shore up Japanese offshore wind domestic supply chain How I got here… National University of Singapore green finance academic Sumit Agarwal Multi-billion-dollar renewables project earmarked for Yindjibarndi native title land Smart Energy Finances: Enel divests 50% of Australian renewable operations to Japanese oil and gas giant Critical minerals investments surged by 30% finds IEA Kung Fu nuns fight climate change One of Southeast Asia’s largest energy storage systems comes online Why turning waste into gas will add value to this Indigenous economy Renewable energy records tumble around Australia as rooftop solar power soars Topsoe supports SGP BioEnergy in renewable fuels production in Panama ‘Poor tropical regions’ suffer greatest economic damage from worsening heatwaves UNEP: Meeting global climate goals now requires ‘rapid transformation of societies’ Analysis: Africa’s unreported extreme weather in 2022 and climate change Partly wind-powered coal ship sails into Newcastle New fossil fuels ‘incompatible’ with 1.5C goal, comprehensive analysis finds Australian offshore wind ‘supercharged’ in Victoria as billions pledged to fast-track projects Goldwind turbine ‘breaks world record for largest rotor diameter’, Chinese media reports BW Ideol to work with developer Taiya on Taiwan floating wind pilot US to boost floating wind power Wind Power in South Korea – an overview GS E&C to develop bioethanol using cassava waste Korean business group has asked the US to make exceptions for Korean EV’s in Inflation Reduction Act Equinor’s Australian offshore wind debut Global energy transition stalls – 2022 Global Status Report in pictures India’s ReNew Power secures $1bn loan for gigascale 24/7 wind-solar-battery project POSCO International to merge with POSCO Energy

Genex starts construction at flagship pumped hydro storage project

Genex has kick-started main construction works for its flagship pumped hydro energy storage project, commencing tunnel digging at the Queensland site.

Genex is developing the Kidston pumped hydro project, which will provide 250MW/2,000MWh of storage capacity, by repurposing two disused gold mine pits.

By transferring water between the two pits, which sit at different heights, Genex can use the site as an energy storage facility.

Genex has undertaken extensive works throughout December and January to establish an underground main access tunnel at the Kidston site that will provide access to a ‘powerhouse’ cavern being established 250 metres below ground level.

The main access tunnel will be dug to be six metres wide and six metres tall and will run for approximately 1.5km to provide access to the main generation and pumping equipment.

The powerhouse will host two 125MW Andritz hydro reversible pump turbines, allowing the turbines to be used to both generate electricity and pump water for energy storage purposes.


Pumped hydro energy storage projects use gravity to store energy by transferring water between reservoirs of differing heights. To store energy, electricity is consumed in the pumping of water to a higher reservoir, which can later be released and used to generate electricity as needed.

The main tunnel will provide access to the underground 250MW hydroelectric facility (Source: Genex).

The main tunnel will provide access to the underground 250MW hydroelectric facility (Source: Genex).

Genex CEO James Harding said the commencement of major engineering works at the site was a significant milestone for the project.

“Following an intense period of site establishment and preparation works, I am delighted that the EPC Contractor JV of McConnell Dowell and John Holland has formally commenced the underground excavation works for the Kidston Pumped Storage Hydro Project,” Harding said.

“This represents a significant milestone in the project construction timeline, which was achieved ahead of schedule. We look forward to working alongside the EPC JV and keeping the market updated as the program continues to push ahead over the course of this year.”

Genex expects to complete the main access tunnel in early 2022, with tunneling operations to continue on a 24/7 basis following the first major blast and excavation works needed to establish the tunnel.

Upon completion – expected in Q4 2024 – the Kidston project will become just the fourth operating pumped hydro project in Australia and one of the first to be newly built for several decades.

The Tumut 3 power station that forms part of the Snowy Hydro scheme, the Shoalhaven Scheme – both in NSW – and the Wivenhoe power station in Queensland are the only currently operational pumped hydro energy storage projects in Australia.

A fifth project is also under development as part of the Snowy 2.0 project, which will become the largest energy storage project in Australia, once operational.

Genex is developing the project after securing a $610 million investment from the Northern Australia Infrastructure Facility and a $47 million grant from the Australian Renewable Energy Agency.

Last year, the ASX-listed Genex undertook a further $115 million fundraising, through the issuance of new shares, to raise the remaining funds needed to undertake the $777 million pumped hydro energy storage project.

Project financials released last year by Genex shows it expects to generate steady revenues from the project, having signed an energy storage service agreement with EnergyAustralia.

Through the contract, Genex will receive regular access payments from EnergyAustralia, which in turn will have the ability to draw upon the Kidston storage project for additional supplies of electricity at critical periods, helping the electricity retailer to mitigate its exposure to electricity price spikes during peak demand periods.

Alongside the Kidston storage project, Genex is developing a portfolio of clean energy projects, including a 50MW solar project co-located at the Kidston site, the 50MW Jemalong solar project in NSW and the 50MW/100MWh Bouldercombe big battery project in Rockhampton.

Michael Mazengarb

Michael Mazengarb is a journalist with RenewEconomy, based in Sydney. Before joining RenewEconomy, Michael worked in the renewable energy sector for more than a decade.


Source